Wild Rose Power Hub Data Centre
- Capacity
- 1,300 MW
- Investment
- Not publicly confirmed
- Score
- 46 / 100
- Checked
- Sep 11, 2026
Capacity basis: AESO connection request (MW)
DC Intel assessment
Early-Stage
Why
Defined 479-acre site, County-led planning process and active 1.3 GW AESO connection request create a real development track.
Risk
Still in area-structure-plan process; request is not allocation; no FID, tenant or final development permit.
Watch
ASP adoption, development permit and firm grid/power arrangement.
Power strategy
Proposed Alberta-grid connection; closed-loop dry cooling.
An AESO request is not an allocation.
Score
Sponsor Quality 9 / 15
Site & Approvals 14 / 20
Power Certainty 12 / 25
Commercial Commitment 3 / 20
Execution Evidence 8 / 20
Total 46 / 100
Scoring method. Not a credit rating or investment advice.