Projects

Wild Rose Power Hub Data Centre

Chinook Development LP Rocky View County Proposed Early-Stage
Capacity
1,300 MW
Investment
Not publicly confirmed
Score
46 / 100
Checked
Sep 11, 2026

Capacity basis: AESO connection request (MW)

DC Intel assessment

Early-Stage

Why

Defined 479-acre site, County-led planning process and active 1.3 GW AESO connection request create a real development track.

Risk

Still in area-structure-plan process; request is not allocation; no FID, tenant or final development permit.

Watch

ASP adoption, development permit and firm grid/power arrangement.

Power strategy

Proposed Alberta-grid connection; closed-loop dry cooling.

An AESO request is not an allocation.

Score

Sponsor Quality 9 / 15
Site & Approvals 14 / 20
Power Certainty 12 / 25
Commercial Commitment 3 / 20
Execution Evidence 8 / 20

Total 46 / 100

Scoring method. Not a credit rating or investment advice.

Sources

Primary

rockyview.ca

Checked Sep 11, 2026

Operations assurance