Teton Digital Black Bear Campus

Teton Digital Swan Hills region Proposed Probable
Capacity
466 MW
Investment
~C$1.3B power component
Score
58 / 100
Checked
Sep 11, 2026

Capacity basis: Proposed behind-the-meter generation (MW)

DC Intel assessment

Probable

Why

Specific 466 MW combined-cycle power design, large controlled site and disclosed permitting/consultation work make it more advanced than an announcement-only campus.

Risk

Final approvals/FID/customer commitments are not public; timeline relies heavily on proponent claims.

Watch

FID, final permits, EPC procurement and customer/offtake commitment.

Power strategy

Proposed 466 MW behind-the-meter combined-cycle natural-gas generation; pathway to larger campus.

An AESO request is not an allocation.

Score

Sponsor Quality 10 / 15
Site & Approvals 15 / 20
Power Certainty 16 / 25
Commercial Commitment 7 / 20
Execution Evidence 10 / 20

Total 58 / 100

Scoring method. Not a credit rating or investment advice.

Sources

Checked Sep 11, 2026

Operations assurance