Malachite One Data Centre
- Capacity
- 930 MW
- Investment
- Up to ~C$20B combined data-centre + power concept
- Score
- 49 / 100
- Checked
- Sep 11, 2026
Capacity basis: Proposed on-site generation at full build (MW)
DC Intel assessment
Early-Stage
Why
Credible energy sponsor, specific Crown-land site adjacent to Banshee gas infrastructure, active AESO load request and detailed integrated gas/power concept.
Risk
Very recent proposal; no major permits, FID, anchor tenant or build evidence yet. Large capex figures are aspirational until contracted.
Watch
Land/permit milestones, AUC/power approvals and customer/FID.
Power strategy
Up to 930 MW on-site gas generation plus active 74.9 MW AESO P3114 load request.
An AESO request is not an allocation.
Score
Sponsor Quality 14 / 15
Site & Approvals 10 / 20
Power Certainty 13 / 25
Commercial Commitment 5 / 20
Execution Evidence 7 / 20
Total 49 / 100
Scoring method. Not a credit rating or investment advice.