Data Centre West of Clive

Undisclosed / local proponent Lacombe County Proposed Speculative
Capacity
19.8 MW
Investment
Not publicly confirmed
Score
28 / 100
Checked
Sep 11, 2026

Capacity basis: Proposed on-site generation (MW)

DC Intel assessment

Speculative

Why

Specific 4.3-acre site and 19.8 MW modular gas-to-compute design are documented.

Risk

Latest confirmed AUC application closed without a decision, weakening the power pathway; sponsor/customer/finance visibility is low.

Watch

A new/active power approval application and municipal construction authorization.

Power strategy

Proposed 19.8 MW on-site natural gas generation with biofuel capability.

An AESO request is not an allocation.

Score

Sponsor Quality 6 / 15
Site & Approvals 9 / 20
Power Certainty 4 / 25
Commercial Commitment 3 / 20
Execution Evidence 6 / 20

Total 28 / 100

Scoring method. Not a credit rating or investment advice.