Crusoe Alsike Energy Park Data Centre

Crusoe / KALiNA Distributed Power Brazeau County Proposed Early-Stage
Capacity
170 MW
Investment
~C$1B related power plant (framework estimate)
Score
54 / 100
Checked
Sep 11, 2026

Capacity basis: Related power-plant capacity (MW)

DC Intel assessment

Early-Stage

Why

Crusoe is a credible AI infrastructure operator and the framework contemplates a site-specific 170 MW plant plus long-term PPA structure.

Risk

Framework agreement is not a project-specific definitive PPA/FID; the withdrawn Crossfield sister project shows these plans can fail before approvals.

Watch

Project-specific development agreement/PPA, AUC/municipal approvals and FID.

Power strategy

Planned 170 MW co-located natural-gas plant; minimum 15-year PPA contemplated.

An AESO request is not an allocation.

Score

Sponsor Quality 15 / 15
Site & Approvals 8 / 20
Power Certainty 14 / 25
Commercial Commitment 10 / 20
Execution Evidence 7 / 20

Total 54 / 100

Scoring method. Not a credit rating or investment advice.