Beacon Indus Data Center Hub
- Capacity
- 1,200 MW
- Investment
- Not publicly confirmed
- Score
- 64 / 100
- Checked
- Sep 11, 2026
Capacity basis: Proposed data-centre load (MW)
DC Intel assessment
Probable
Why
Municipal planning/redesignation is approved, federal review did not require further assessment, and the 1.494 GW power-plant AUC hearing has been held.
Risk
No final AUC decision, FID, anchor customer or data-hall development permits yet.
Watch
AUC decision followed by data-centre development permits and FID.
Power strategy
Proposed 1.494 GW on-site natural-gas generation.
An AESO request is not an allocation.
Score
Sponsor Quality 11 / 15
Site & Approvals 17 / 20
Power Certainty 18 / 25
Commercial Commitment 8 / 20
Execution Evidence 10 / 20
Total 64 / 100
Scoring method. Not a credit rating or investment advice.