Beacon Data Centers Sturgeon County Proposed Probable
Capacity
800 MW
Investment
Not publicly confirmed
Score
67 / 100
Checked
Sep 11, 2026

Capacity basis: Proposed data-centre load (MW)

DC Intel assessment

Probable

Why

Master site development permit is approved/amended and grading activity has begun; federal assessment trigger cleared; dedicated 920 MW power application is well advanced.

Risk

AUC power decision, FID, financing, anchor customer and equipment commitments remain outstanding.

Watch

AUC decision, power-plant approval, FID and named customer/tenant.

Power strategy

Proposed 920 MW on-site natural-gas generation.

An AESO request is not an allocation.

Score

Sponsor Quality 11 / 15
Site & Approvals 18 / 20
Power Certainty 18 / 25
Commercial Commitment 8 / 20
Execution Evidence 12 / 20

Total 67 / 100

Scoring method. Not a credit rating or investment advice.