Beacon Heartland AI Data Center Hub
- Capacity
- 800 MW
- Investment
- Not publicly confirmed
- Score
- 67 / 100
- Checked
- Sep 11, 2026
Capacity basis: Proposed data-centre load (MW)
DC Intel assessment
Probable
Why
Master site development permit is approved/amended and grading activity has begun; federal assessment trigger cleared; dedicated 920 MW power application is well advanced.
Risk
AUC power decision, FID, financing, anchor customer and equipment commitments remain outstanding.
Watch
AUC decision, power-plant approval, FID and named customer/tenant.
Power strategy
Proposed 920 MW on-site natural-gas generation.
An AESO request is not an allocation.
Score
Sponsor Quality 11 / 15
Site & Approvals 18 / 20
Power Certainty 18 / 25
Commercial Commitment 8 / 20
Execution Evidence 12 / 20
Total 67 / 100