AHI Red Deer / Blindman Industrial Park AI Data Centre
- Capacity
- 10 MW
- Investment
- Not publicly confirmed
- Score
- 78 / 100
- Checked
- Sep 11, 2026
Capacity basis: Phase 1 on-site generation (MW)
DC Intel assessment
Highly Credible
Why
Red Deer County approved Phase 1 with conditions and evidence shows foundations / M&E work underway. Ranking applies to the initial 10 MW phase, not uncommitted 200 MW+ ambitions.
Risk
Sponsor is less proven in hyperscale delivery; later hydrogen and campus expansion claims are not yet execution evidence.
Watch
Completion/energization of Phase 1 and evidence of customer deployment.
Power strategy
10 MW Phase 1 on-site natural gas generation; future hydrogen blending is proposed.
An AESO request is not an allocation.
Score
Sponsor Quality 10 / 15
Site & Approvals 18 / 20
Power Certainty 19 / 25
Commercial Commitment 12 / 20
Execution Evidence 19 / 20
Total 78 / 100
Scoring method. Not a credit rating or investment advice.