Projects

AHI Red Deer / Blindman Industrial Park AI Data Centre

Alberta Hydrogen Infrastructure / Havenz Red Deer County Under construction Highly Credible
Capacity
10 MW
Investment
Not publicly confirmed
Score
78 / 100
Checked
Sep 11, 2026

Capacity basis: Phase 1 on-site generation (MW)

DC Intel assessment

Highly Credible

Why

Red Deer County approved Phase 1 with conditions and evidence shows foundations / M&E work underway. Ranking applies to the initial 10 MW phase, not uncommitted 200 MW+ ambitions.

Risk

Sponsor is less proven in hyperscale delivery; later hydrogen and campus expansion claims are not yet execution evidence.

Watch

Completion/energization of Phase 1 and evidence of customer deployment.

Power strategy

10 MW Phase 1 on-site natural gas generation; future hydrogen blending is proposed.

An AESO request is not an allocation.

Score

Sponsor Quality 10 / 15
Site & Approvals 18 / 20
Power Certainty 19 / 25
Commercial Commitment 12 / 20
Execution Evidence 19 / 20

Total 78 / 100

Scoring method. Not a credit rating or investment advice.

Sources

Checked Sep 11, 2026

Operations assurance